Makarpura GIDC Industrial Chiller

Emergency 50-Ton Chiller Recovery

The Emergency

At 2:00 AM, we received a distress call from a pharmaceutical chemical plant in Makarpura GIDC. Their primary 50-ton water-cooled chiller had tripped on high pressure, halting a critical cooling jacket process.

If the temperature of the reactor was not stabilized within 4 hours, they risked losing ₹15 Lakhs worth of chemical batch.

Diagnostics

Our heavy industrial squad arrived on-site within 45 minutes.

  1. Thermal Imaging: Scans showed extreme hotspots on the compressor head.
  2. Pressure Tests: Discharge pressure was abnormally high, while suction was dropping.
  3. Water Flow Analysis: The condenser water pump was working, but the delta-T (temperature difference) across the condenser barrel was negligible.

Conclusion: The condenser tubes were heavily scaled with calcium deposits, severely restricting heat exchange and causing the compressor to overheat and trip on HP (High Pressure).

The Engineering Fix

  1. Chemical Descaling: We isolated the condenser barrel and initiated a rapid, aggressive descaling process using industrial-grade, non-corrosive descalants.
  2. Flushing: Flushed the system with neutralizing agents to prevent tube pitting.
  3. Calibration: Re-calibrated the expansion valve to account for the restored heat exchange efficiency.

Result

The chiller was brought back online at 4:30 AM. Condensing pressures dropped back to factory specifications, and the chemical reactor was stabilized saving the batch. The client immediately signed a 3-year AMC (Annual Maintenance Contract) with Atlas Aircon.